Indianola Bridge Rehab, ODOT Stage 2 plans

GENCA Summary

Project description:

Rehab of Indianola Bridge over Glen Echo Ravine, minor asphalt roadway work on either side of bridge, construction of storm sewers and relocation of a 16″ waterline.

Bridge:

-Patching of existing concrete spandrel and wing walls (see image clip of elevations from ODOT plans below), installation of a composite fiber wrap system (CFRP) on underside of concrete arch, excavation and waterproofing of bridge structure from above, inspection and possible replacement of existing tie-rods.

-Existing stairs will remain but may be closed during construction.

-Notes indicate that bird mural is not to be disturbed.

-Approximately 7 trees within the construction limits will be removed (see image clip of construction limit from ODOT plans below). Notes indicate all other trees are not to be disturbed.

image  image

Traffic:

-Bridge will be closed to all traffic during construction. Arcadia to Cliffside will be open to local traffic only.

-Traffic plan currently directs detour traffic down Arcadia, to High street and back up to Weber road to avoid the bridge construction.

Links:

To view the complete plans, click here.

To read the GENCA letter to ODOT with comments, questions and requests, click here.

As we learn more, we will update neighbors here and on facebook. If you do not receive neighborhood mailchimp emails, you can sign up here. You can also contact us at glenechoproject@gmail.com with comments or questions.